✏️ Explanatory Question
The trade-off triangle represents the relationship between:
Scope
Resources
Schedule
The rule is simple: if one side changes, at least one other side must also change.
For example:
Adding custom functionality (scope ↑) may require more time or resources.
Reducing timeline may require reducing scope or adding resources.
During fit-gap analysis, this triangle helps architects make realistic decisions when addressing gaps.