Q You are working on a project that has undefined requirements and new requirements are expected to occur during the project. What methodology would best suit this type of project?
ID: #12150
Module 1: Introduction to Visual Studio
161 views
Question Info
#12150Q ID
EasyDifficulty
Module 1: Introduction to Visual StudioTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer: Option B
Explanation
- A. Incorrect: Waterfall is best used when all the requirements are defined at the beginning.
- B. Correct: Agile is useful when requirements are undefined and additional requirements are expected throughout the project life cycle.
- C. Incorrect: Spiral is a better methodology for dealing with complex projects that need risk assessment.