QLoad and Longevity test can be triggered parallelly.

ID: #24008 Component and Integration Pipelines 178 views
Question Info
#24008Q ID
DifficultDifficulty
Component and Integration PipelinesTopic

Choose the Best Option

Click any option to instantly check if you're correct.

  • A False ✔ ✖
  • B True ✔ ✖
Correct Answer

Explanation

True

Load testing and Longevity testing can be triggered in parallel since they serve different purposes:

  • Load testing evaluates system performance under expected or peak load conditions.
  • Longevity testing (also called endurance testing) checks system stability over an extended period.

Running them in parallel can help save time and identify performance bottlenecks efficiently.

Today: 0 answered · 0 correct
Save progress
Free account

Want to remember what you got wrong?

Create a free account in seconds to track your score, revisit mistakes and continue Continuous Deployment where you left off.

  • Save your progress & streak
  • Topic-wise quizzes & scores
  • Bookmark tricky questions
  • Printable MCQ sets
Practice smarterFree account · save progress
Sign up free

Share This Question

Challenge a friend or share with your study group.