MCQ Single Best Answer Easy

QAt what point of a project should you begin planning for cutover?

ID: #24604 Cutover strategy for Dynamics 365 solutions 10 views
Question Info
#24604Q ID
EasyDifficulty
Cutover strategy for Dynamics 365 solutionsTopic

Choose the Best Option

Click any option to instantly check if you're correct.

  • A As part of the Solution blueprint review or soon afterward
  • B As part of go-live planning
  • C After user acceptance testing is complete
Correct Answer: Option A

Explanation

✔️ The first review of the cutover strategy should be conducted as part of the Solution blueprint review or soon afterward. It might be tempting to postpone the cutover strategy review because it can be perceived as an activity that happens at go-live.

❌ User acceptance testing (UAT) happens late in a project; cutover strategy should be reviewed much sooner.