QThis screenshot shows an example Kanban board. What do the two numbers contained in the orange box, 0/2, mean?

ID: #22695 Azure Boards - Azure DevOps 93 views
Question Info
#22695Q ID
EasyDifficulty
Azure Boards - Azure DevOpsTopic
Question image for #22695

Choose the Best Option

Click any option to instantly check if you're correct.

  • A The first number is the number of work items in the Code Review columns, while the second number is the Work in Progress (WIP) limit.
  • B The first number is the maximum number of Work in Progress items allowed, and the second number is how many items are left to be done.
  • C The first number is the number of work items in the Doing column, and the second number is how many work items are done.
Correct Answer: Option A

Explanation

You can change the WIP under Settings > Columns.