MCQ Single Best Answer Difficult

QSteps to be carried out to release the application first time comes under ___________.

ID: #23999 Component and Integration Pipelines 84 views
Question Info
#23999Q ID
DifficultDifficulty
Component and Integration PipelinesTopic

Choose the Best Option

Click any option to instantly check if you're correct.

  • A Both the options
  • B Release Plan
  • C Release Strategy
  • D None of the options
Correct Answer: Option B

Explanation

The correct answer is: "Release Plan"

A Release Plan outlines the steps required to release an application for the first time, including development, testing, deployment, and post-release activities.

  • Release Strategy focuses on long-term planning for multiple releases.
  • Release Plan is specific to a particular release, especially the first deployment.

Share This Question

Challenge a friend or share with your study group.