MCQ Practice Single Best Answer Topic: Prepare to go-live with finance and operations apps

Q Your customer is ready to go live and request to deploy the production environment. What must be done first?

Question ID
#24579
Subchapter
Prepare to go-live with finance and operations apps
Action
Choose one option below

Choose Your Answer

Click an option to check whether your answer is correct.

  • A You must deploy a new environment and call it production.
  • B Contact Dynamics Service Engineering (DSE).
  • C Complete a go-live review with the Microsoft FastTrack team.
Correct Answer: C

Explanation

All finance and operations apps customers must complete a go-live review with the Microsoft FastTrack team before their production environment can be deployed. This assessment should be successfully completed before you request your production environment.