QYour customer is ready to go live and request to deploy the production environment by contacting the Microsoft FastTrack team. What happens next?
ID: #24580
Prepare to go-live with finance and operations apps
15 views
Question Info
#24580Q ID
DifficultDifficulty
Prepare to go-live with finance and operations appsTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer: Option C
Explanation
After the checklist is submitted, a Microsoft solution architect reviews the project and provides an assessment that describes the potential risks, best practices, and recommendations for a successful go-live of the project. In some cases, the solution architect might highlight risk factors and ask for a mitigation plan. When the assessment is completed, the solution architect indicates that you're ready to request the production environment in Lifecycle Services.
Continue Practice
Share
Share This Question
Challenge a friend or share with your study group.
More from This Topic