Q
You are tasked with setting up the master planning module in Microsoft Dynamics 365 Supply Chain Management. The company has a complex production setup with various BOM levels, and they frequently encounter delays due to material and capacity constraints.
You need to ensure that delays at lower BOM levels are reflected accurately in the master planning run to prevent cascading delays across the production process.
What three actions should you perform? Each correct answer presents part of the solution. Choose 3.
Question Info
Select All That Apply
Tick every correct option, then press Check Answer.
Explanation
Option A is correct because approving or firming the production orders at the top of the BOM structure ensures that delays are kept and all underlying components are updated accordingly. Option B is correct as action messages help in identifying and adjusting the dates of planned orders affected by delays. Option C is correct because configuring the coverage group settings to calculate delays ensures that delays are calculated for each item in the group. Option D is incorrect because increasing lead times does not address the issue of delays not being applied to all items in the BOM structure. Option E is incorrect as disabling the delay calculation feature would prevent any delays from being calculated, which is not the goal. Option F is incorrect because setting the start time for the calculation of delays to a future date would not solve the problem of delays not being applied to all items immediately.
Share This Question
Challenge a friend or share with your study group.