You use Asset management in Dynamics 365 Supply Chain Management.
You have an asset with a capacity of 100 and a remainder value of 100.
You need to identify what the remainder value represents.
What should you identify?
Question Info
Choose the Best Option
Click any option to instantly check if you're correct.
Explanation
The correct answer is that the remainder value represents the amount of time that the asset can spend on future work. In Asset Management, the remainder value is calculated as the difference between the asset's total capacity and the reserved value (time already allocated to planned work). It does not reflect the total capacity load, completed work, or pending work orders directly. Instead, it indicates the unused portion of capacity that is still available for scheduling future tasks.