You are tasked with enhancing the efficiency of master planning jobs in Microsoft Dynamics 365 Supply Chain Management.

It is crucial to streamline these processes to mitigate the impact on overall performance while ensuring uninterrupted operations.

You need to improve the performance of master planning without affecting the current operations.

What three actions should you perform? Each correct answer represents part of the solution. Choose 3.

ID: #25471 Practice Assessment 8 views
Question Info
#25471Q ID
ModerateDifficulty
Practice AssessmentTopic

Select All That Apply

Tick every correct option, then press Check Answer.

  • A Actions
  • B Number of orders in firming bundle
  • C Time fences
  • D Number of tasks in helper task bundle
  • E Use of cache, Number of threads
Correct Answer

Explanation

The 'Number of threads' parameter allows you to adjust the master scheduling process to help improve performance on the specific data set. It specifies the total number of threads that will be used to run master planning and causes parallelization of the master planning run, which helps decrease the running time.

Use master planning in Dynamics 365 Supply Chain Management - Training | Microsoft Learn

Improve master planning performance - Documentation - Training | Microsoft Learn