Practice Assessment Practice Assessment Question #25527
Multiple Choice Moderate

Q

You are tasked with configuring up a new master plan in Microsoft Dynamics 365 Supply Chain Management.

You are utilizing multiple master plans to support daily operations and explore various planning strategies.

You need to set up a new master plan that considers the maximum capacity of resources for order scheduling within a specific future timeframe.

What two actions should you perform? Each correct answer presents part of the solution.

ID: #25527 Practice Assessment 6 views
Question Info
#25527Q ID
ModerateDifficulty
Practice AssessmentTopic

Select All That Apply

Tick every correct option, then press Check Answer.

  • A Enter the number of days that capacity should be planned for planned production orders.
  • B Set the Capacity option to Yes on the Time fences in days FastTab of the Master plans page.
  • C Set the Capacity option to No on the Time fences in days FastTab of the Master plans page.
  • D Enter the number of days in the Coverage option on the Time fences in days FastTab of the Master plans page.
  • E Set the Firming option to Yes on the Time fences in days FastTab of the Master plans page.
Correct Answer

Explanation

To consider the maximum capacity of resources when scheduling orders for a specific future period, you need to set the Capacity option to Yes and specify the number of days that capacity should be planned for planned production orders. Setting the Capacity option to No would not consider the maximum capacity of resources. The Coverage option is used to indicate the planning horizon, not the capacity of resources. The Firming option is used to automatically convert planned orders to production and purchase orders, not to consider the capacity of resources.

Auto-firming - Training | Microsoft Learn

Master plans overview - Documentation - Training | Microsoft Learn

Share This Question

Challenge a friend or share with your study group.