QA can complete a task in 25 days, and B can complete the same task in 20 days. Together, they work for 5 days, and then A stops working. How long will it take B to finish the remaining work?

ID: #4618 Time and Work 177 views
Question Info
#4618Q ID
Not SetDifficulty
Time and WorkTopic

Choose the Best Option

Click any option to instantly check if you're correct.

  • A 12
  • B 13
  • C 11
  • D 10
Correct Answer

Explanation

If A can complete a task in 25 days,
and B can complete the same task in 20 days, then their combined daily rate of progress is 1/25 + 1/20 of the task per day.
Therefore, their 5 days of work together represents 5 * (1/25 + 1/20) = 9/20 of the task.
This means that the remaining work to be done is 1 - 9/20 = 11/20 of the task.
If B can complete 1/20 of the task in one day, then it will take him 11 days to complete the remaining 11/20 of the task