QIf A and B can complete a piece of work together in 30 days, and after A works for 16 days, B takes 44 days to finish the remaining work alone, how many days will it take B to complete the entire work by themselves?
ID: #4641
Time and Work
271 views
Question Info
#4641Q ID
Not SetDifficulty
Time and WorkTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer
Explanation
If we let A's 1 day's work be represented by x and B's 1 day's work be represented by y,
then the equations x + y = 1 and 16x + 44y = 1 can be used to determine that x = 1 and y = 1.
This means that B's 1 day's work is equal to 1.
Therefore, B alone will take 60 days to finish the entire work