Q If X can complete a task in 20 days and Y can complete it in 12 days, and X starts the work alone and Y joins him after 4 days, how long does the work take to complete?
ID: #4633
Time and Work
171 views
Question Info
#4633Q ID
Not SetDifficulty
Time and WorkTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer
Explanation
The work rate of X is 1/20 of the task per day, and the work rate of Y is 1/12 of the task per day. X works alone for 4 days, completing 1/5 of the task.
The remaining work is 4/5 of the task, and the combined work rate of X and Y is 2/15 of the task per day.
Therefore, it will take X and Y a total of 6 days to complete the remaining work.
The total time taken for the work to be completed is 6 days + 4 days = 10 days