QIf A and B can complete a task in 15 days and 10 days, respectively, and they start working together but B has to leave after 2 days, and A completes the remaining work on their own, how long does it take to complete the whole task?
ID: #4636
Time and Work
170 views
Question Info
#4636Q ID
Not SetDifficulty
Time and WorkTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer
Explanation
The combined work rate of A and B is 1/6 of the task per day, and they work together for 2 days,
completing 1/3 of the task.
The remaining work is 2/3 of the task, and A's work rate is 1/15 of the task per day.
Therefore, it will take A 10 days to complete the remaining work.
The total time taken for the task to be completed is 10 days + 2 days = 12 days