QIf A can complete a work in 24 days, B can finish it in 9 days, and C can finish it in 12 days, and B and C start the work but are forced to leave after 3 days, how long will it take A to finish the remaining work?

ID: #4640 Time and Work 143 views
Question Info
#4640Q ID
Not SetDifficulty
Time and WorkTopic

Choose the Best Option

Click any option to instantly check if you're correct.

  • A 10
  • B 16
  • C 15
  • D 21
Correct Answer

Explanation

If B and C can complete 1/36 of the work per day together,
and they work for 3 days before leaving, then the remaining work is 5/12 of the task.
Since A can complete 1/24 of the work per day,
it will take A 10 days to finish the remaining work