QIf A can complete a piece of work in 80 days, he works on it for 10 days, and B alone finishes the remaining work in 42 days, how long will it take for A and B working together to finish the work?
ID: #4647
Time and Work
170 views
Question Info
#4647Q ID
Not SetDifficulty
Time and WorkTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer
Explanation
A can complete the work in 80 days, so the amount of work he completes in 1 day is (1/80) of the total work. A works on the job for 10 days, so he completes a total of (1/80) * 10 = 1/8 of the total work. The remaining work is 1 - 1/8 = 7/8 of the total work. B alone finishes the remaining work in 42 days, so the amount of work he completes in 1 day is (7/8) / 42 = 1/48 of the total work. When A and B work together, their combined 1 day's work is (1/80) + (1/48) = 8/240 = 1/30 of the total work. Since they complete (1/30) of the total work in 1 day, it will take them 30 days to complete the entire work.
Continue Practice
Share
Share This Question
Challenge a friend or share with your study group.
More from This Topic