QIf 2 men and 3 boys can complete a piece of work in 10 days, and 3 men and 2 boys can complete the same work in 8 days, how long will it take for 2 men and 1 boy to do the work ?
ID: #4649
Time and Work
221 views
Question Info
#4649Q ID
Not SetDifficulty
Time and WorkTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer
Explanation
Let's suppose that the work done by 1 man in 1 day is x, and the work done by 1 boy in 1 day is y. Then the work done by 2 men and 3 boys in 1 day is 2x + 3y, and the work done by 3 men and 2 boys in 1 day is 3x + 2y. We are given that 2 men and 3 boys can complete the work in 10 days, so 2x + 3y = 1/10. We are also given that 3 men and 2 boys can complete the work in 8 days, so 3x + 2y = 1/8. Solving these equations for x and y, we get x = 7/200 and y = 1/100. The work done by 2 men and 1 boy in 1 day is (2 * 7/200) + (1/100) = 16/200 = 2/25 of the total work. Since 2 men and 1 boy complete (2/25) of the work in 1 day, it will take them 25/2 = 12 1/2 days to complete the entire work.
Continue Practice
Share
Share This Question
Challenge a friend or share with your study group.
More from This Topic