Q: 56 men can complete a piece of work in 24 days .In how many days can 42 men complete the same piece of work?
[Bank PO 2008]
B
Answer:
B
Explanation:
Solution
let the required number of days be x.Less men,more days (indirect proportion)
42:56::24:x
42x=56×24
x=56×24/42
x=6