Q56 men can complete a piece of work in 24 days .In how many days can 42 men complete the same piece of work?
ID: #5614
Chain Rule
172 views
Question Info
#5614Q ID
DifficultDifficulty
Chain RuleTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer: Option B
Explanation
Solution
let the required number of days be x.Less men,more days (indirect proportion)
42:56::24:x
42x=56×24
x=56×24/42
x=6