Q30 Men can do a piece of work in 16 days .How many men would be required to do the same work in 20 days?
ID: #5615
Chain Rule
216 views
Question Info
#5615Q ID
DifficultDifficulty
Chain RuleTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer: Option B
Explanation
Solution
let the required number of men be x.
more days ,less men(Indirect proportion)
20:16::30:x
20x=16×30
x=16×30/20
x=24