QA group of worker promise to complete a piece of work in 10 days but 5 of them do not report for work if it took the remaining workers 12 days to complete the work then the number of workers original hired was?
ID: #5616
Chain Rule
217 views
Question Info
#5616Q ID
DifficultDifficulty
Chain RuleTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer
Explanation
Solution
Let the required number of workers originally hired be x.
less workers,more days(indirect proportion)
(x-5):x::10:12
12(x-5)=10x
2x=60
x=30