You are managing warehouse processes within Microsoft Dynamics 365 Supply Chain Management across various warehouses with different storage needs and various turnover rates for items.

You need to ensure that the system automatically converts planned orders into purchase orders within a specific time frame without manual intervention.

What two actions should you perform? Each correct answer presents part of the solution. Choose 2.

ID: #25494 Practice Assessment 8 views
Question Info
#25494Q ID
ModerateDifficulty
Practice AssessmentTopic

Select All That Apply

Tick every correct option, then press Check Answer.

  • A Set up the Automatic firming time fence in the Coverage groups on the Other FastTab.
  • B Increase the default order settings for minimum order quantity.
  • C Adjust the lead time in the Item coverage settings.
  • D Enable the Override time fences option in the master plan's Time fences in days FastTab.
Correct Answer

Explanation

The Automatic firming time fence in the Coverage groups on the Other FastTab is used to define the period within which planned orders are automatically firmed. Increasing the minimum order quantity, adjusting lead time, or enabling the Override time fences option does not directly enable auto-firming of planned orders.

Auto-firming - Training | Microsoft Learn

Time fences in days - Documentation - Training | Microsoft Learn