You use Dynamics 365 Supply Chain Management for Production control.

You have a working time template named Template1 that is applied to a working time calendar. The working time template has the following configurations:

  • Workday: 08:00 to 17:00
  • One-hour break: 12:00 to 13:00
  • Workdays: Monday through Friday
  • Weekend: Saturday and Sunday

You have a resource named Resource1 that requires 16 hours of processing time to complete an order.

You apply Template1 to the calendar of Resource1.

You schedule an order for Resource1 to begin on Monday at 08:00.

When will the order be complete?

ID: #25495 Practice Assessment 8 views
Question Info
#25495Q ID
ModerateDifficulty
Practice AssessmentTopic

Choose the Best Option

Click any option to instantly check if you're correct.

  • A Tuesday at 12:00
  • B Tuesday at 16:00
  • C Tuesday at 17:00
  • D Wednesday at 08:00
Correct Answer

Explanation

Resource1 works 8 productive hours per day (08:00-12:00 and 13:00-17:00). On Monday, 8 hours are completed. The remaining 8 hours carry into Tuesday, which provides another full 8-hour workday. Therefore, the 16-hour requirement is met exactly at the end of Tuesday's work shift (17:00). Options A and B underestimate or miscount the available work hours, while option D incorrectly extends the schedule into Wednesday.

Create working time templates - Training | Microsoft Learn