You use Dynamics 365 Supply Chain Management.

You are configuring master planning.

You create a new item and set the item to automatically create planned orders.

You need to perform the following actions for the item:

  • Review the expected inventory levels by period.
  • Review the planned orders by period
  • Edit the planned orders.

What should you do?

ID: #25496 Practice Assessment 8 views
Question Info
#25496Q ID
ModerateDifficulty
Practice AssessmentTopic

Choose the Best Option

Click any option to instantly check if you're correct.

  • A Run the master plan.
  • B Set the item coverage group to Minimum.
  • C Set the item coverage group to Requirement.
  • D Use the Supply Schedule page.
Correct Answer

Explanation

The correct answer is Use the Supply Schedule page because it is the only feature in Dynamics 365 Supply Chain Management that provides a period-based view of expected inventory levels, demand, and planned supply while also enabling planners to directly edit planned orders. Running the master plan is necessary to generate planned orders but does not provide the required review or editing functionality, and coverage groups (Minimum or Requirement) only control how master planning calculates safety stock or requirement-based supply-not how orders are displayed or modified. Thus, only the Supply Schedule page satisfies all requirements.

Supply schedule - Training | Microsoft Learn