QIf A is twice as efficient as B at completing a task, and B can finish the work in 12 days independently, how many days will it take A and B to complete the work together?
ID: #4638
Time and Work
153 views
Question Info
#4638Q ID
Not SetDifficulty
Time and WorkTopic
Your Answer
Choose the Best Option
Click any option to instantly check if you're correct.
Correct Answer
Explanation
"If B's work rate is 1/12 of the task per day,
and A's work rate is twice as fast as B's, meaning it is 1/6 of the task per day,
then the combined work rate of A and B is
(1/6 + 1/12) of the task per day, which is equal to 1/4 of the task per day.
Therefore, it will take A and B 4 days to complete the work together.