Q If A and B can complete a work in 8 days, B and C can complete it in 12 days, and A, B, and C can finish it in 6 days, how long will it take A and C to complete the work together?

ID: #4639 Time and Work 152 views
Question Info
#4639Q ID
Not SetDifficulty
Time and WorkTopic

Choose the Best Option

Click any option to instantly check if you're correct.

  • A 13
  • B 16
  • C 8
  • D 5
Correct Answer: Option C

Explanation

If the combined work rate of A, B, and C is 1/6 of the task per day,
the work rate of A and B is 1/8 of the task per day,
and the work rate of B and C is 1/12 of the task per day,
then the work rate of A and C is
(2 x 1/8 - 1/12) of the task per day,
which is equal to 1/8 of the task per day.
Therefore, A and C will take 8 days to complete the work together